Canadian Plaza Redevelopment Project Update – November 7, 2014

  • Underground civil services are ongoing with most of the sanitary and sewer installed. Much of the site has received fill and is being prepared for final asphalt and concrete paving.
  • Interlocking and landscaping for the Duty Free building are now completed.
  • Temporary asphalt is placed and the traffic is now running on the south side of the bridge ramp .
  • Concrete pavement for entrance of the Duty Free building is now completed.
  • Drywall at the maintenance building is underway in the office areas while the exterior and interior masonry is completed.